Engineering Inc. - July/August 2007 - 16
KEy PLAyErS By the Numbers n Amount of dirt excavated: 15 million cubic tons. n Concrete used to replace the dirt: 3.8 million cubic feet. n Steel used: 26,000 linear feet. n Traffic management system: 400 video cameras, 130 electronic message signs, 30 infrared height detectors, six emergency response systems. n Reduction in air pollution due to central artery project: 12 percent citywide. n Maximum number of construction workers on project: approximately 5,000. n Number of construction contracts executed: 109. n Underground utilities relocated: 29 miles of gas, electric, water, sewer, telephone and other lines managed and maintained by 31 companies. n Deepest point: 120 feet at Dewey Square, where it passes beneath the red Line subway. n New parkland: 300 acres (27 acres reclaimed from the elevated highway). n Toxic contaminants hauled away: 435,000 cubic yards of soil and other debris. process of transporting them, and balancing their weight within the water, even more complex. Using remote control cameras, engineers positioned the pieces and connected them like giant Lego blocks. Constructing the last link between the ITT and I-90 created another challenge. Engineers had to dig under commuter rail lines carrying more than 150 trains and 100,000 passengers a day, without disrupting the tracks. Once again, workers faced the problem of soft soil that couldn’t support tunneling. Any attempt to remove the soft soil under the tracks risked derailing the entire project. That’s when one contractor proposed a new and radical solution: Freeze the soil during the tunneling process using 2,000 pipes located eight feet apart, each filled with a brine refrigerant solution chilled to minus 30 degrees Fahrenheit. “It was like creating a manmade permafrost,” Bertoulin says. Workers mined 18 inches into the frozen soil, creating a void using the tunneljacking process. The tunnel jacking required 10,000 PSI to move the 35,000-ton sections at a rate of three feet per day until they were in place. The process took three years to complete, but left the structures on the surface untouched. In September 2001, a massive leak occurred in the section where the land and sea tunnels met. Rapidly rising water inundated expensive cranes and other equipment and made the tunnel impassable. Although crews began working on the problem immediately, it took divers nearly eight weeks to identify and plug the leak. By then, the opening of the tunnel was delayed by four months. Driving Results FReD SALvuCCI An engineer and former Massachusetts transportation secretary (1983–1990), he is credited with first envisioning the concept of the Big Dig and generating the project’s initial financial and political support. SALLy PeRRIn Former deputy project manager for the Bechtel/ Parsons Brinckerhoff team, she oversaw environmental mitigation, real estate and traffic management as they prepared for construction. JoHn KenneDy Senior principal at vanasse Hangen Brustlin, Inc., he designed the traffic management plan that maintained safe and efficient traffic operations during the 15-year Big Dig construction period. PAuL HARRIngTon Director of structural division at Fay Spofford & Thorndike, Inc., he developed the underpinning (foundation support) system that allowed tunnel construction to proceed without affecting existing transit/rail systems or surface structures. SenA KuMARASenA HnTB associate vice president, he served as project engineer and project manager during the design and construction of the Leonard P. Zakim Bunker Hill Bridge, the widest cablestayed bridge in the world. The old elevated High Bridge over the Charles River is demolished in early 2004. Massachusetts turnpike authority The final piece of the project was the engineering of the tunnel beneath I-93. To clear space for the underground highway, engineers had to build corridors to relocate pipes, cables and other infrastructure that fills virtually every square inch of subterranean Boston. At one point, they had to dig underneath three levels of subterranean transportation systems—subway lines, heavy rail and a bus station—and create a tunnel space only 36 inches beneath the subway. “Essentially, we had to create a parallel set of walls with huge crossbeams beneath the existing raised structure in order to build the tunnel. The ground had to support both the existing steel and concrete structure and the tunnel box,” says Frank Leathers, a geotechnical engineer and president of GEI Consultants, Inc., which designed one section of the slurry walls for the project. Prior to the Big Dig, Leathers says, the slurry wall module building method had never been attempted on such a large scale. Project planners also recognized the need to replace a deteriorating three-lane double-decker bridge over the Charles River used to connect the tunnel to the interstate. Further complicating the project, engineers decided it was necessary to build around the existing bridge structure so that traffic continued to flow during construction. Today, the $100 million cable-stayed Leonard P. Zakim Bunker Hill Bridge, the widest asymmetrical bridge ever built, carries 10 lanes of traffic—eight through the legs of twin towers 16 ENGINEERING INC. July / AuGust 2007
Engineering Inc. - July/August 2007
Table of Contents for the Digital Edition of Engineering Inc. - July/August 2007
Call for Entries
Contents
From ACEC to You
News & Notes
Market Watch
Legislative Action
The Big Dig
Risky Engineering
2007 Professional Liability Survey
Institute For Business Management Fall 2007 Course Catalog
Roadside Technology
2007 Convention Wrap-Up
2007-2008 Excom
2007 Fall Conference Primer
Business Insights
Technology
Members in the News
One on One
Engineering Inc. - July/August 2007 - Cover1
Engineering Inc. - July/August 2007 - Cover2
Engineering Inc. - July/August 2007 - Call for Entries
Engineering Inc. - July/August 2007 - C2
Engineering Inc. - July/August 2007 - C3
Engineering Inc. - July/August 2007 - C4
Engineering Inc. - July/August 2007 - C5
Engineering Inc. - July/August 2007 - C6
Engineering Inc. - July/August 2007 - C7
Engineering Inc. - July/August 2007 - C8
Engineering Inc. - July/August 2007 - Contents
Engineering Inc. - July/August 2007 - From ACEC to You
Engineering Inc. - July/August 2007 - 3
Engineering Inc. - July/August 2007 - News & Notes
Engineering Inc. - July/August 2007 - 5
Engineering Inc. - July/August 2007 - 6
Engineering Inc. - July/August 2007 - Market Watch
Engineering Inc. - July/August 2007 - 8
Engineering Inc. - July/August 2007 - 9
Engineering Inc. - July/August 2007 - Legislative Action
Engineering Inc. - July/August 2007 - 11
Engineering Inc. - July/August 2007 - The Big Dig
Engineering Inc. - July/August 2007 - 13
Engineering Inc. - July/August 2007 - 14
Engineering Inc. - July/August 2007 - 15
Engineering Inc. - July/August 2007 - 16
Engineering Inc. - July/August 2007 - 17
Engineering Inc. - July/August 2007 - Risky Engineering
Engineering Inc. - July/August 2007 - 19
Engineering Inc. - July/August 2007 - 20
Engineering Inc. - July/August 2007 - 21
Engineering Inc. - July/August 2007 - 22
Engineering Inc. - July/August 2007 - 2007 Professional Liability Survey
Engineering Inc. - July/August 2007 - 24
Engineering Inc. - July/August 2007 - Institute For Business Management Fall 2007 Course Catalog
Engineering Inc. - July/August 2007 - I2
Engineering Inc. - July/August 2007 - I3
Engineering Inc. - July/August 2007 - I4
Engineering Inc. - July/August 2007 - I5
Engineering Inc. - July/August 2007 - I6
Engineering Inc. - July/August 2007 - I7
Engineering Inc. - July/August 2007 - I8
Engineering Inc. - July/August 2007 - I9
Engineering Inc. - July/August 2007 - I10
Engineering Inc. - July/August 2007 - I11
Engineering Inc. - July/August 2007 - I12
Engineering Inc. - July/August 2007 - I13
Engineering Inc. - July/August 2007 - I14
Engineering Inc. - July/August 2007 - I15
Engineering Inc. - July/August 2007 - I16
Engineering Inc. - July/August 2007 - I17
Engineering Inc. - July/August 2007 - I18
Engineering Inc. - July/August 2007 - I19
Engineering Inc. - July/August 2007 - I20
Engineering Inc. - July/August 2007 - I21
Engineering Inc. - July/August 2007 - I22
Engineering Inc. - July/August 2007 - I23
Engineering Inc. - July/August 2007 - I24
Engineering Inc. - July/August 2007 - 25
Engineering Inc. - July/August 2007 - 26
Engineering Inc. - July/August 2007 - 27
Engineering Inc. - July/August 2007 - Roadside Technology
Engineering Inc. - July/August 2007 - 29
Engineering Inc. - July/August 2007 - 30
Engineering Inc. - July/August 2007 - 31
Engineering Inc. - July/August 2007 - 2007 Convention Wrap-Up
Engineering Inc. - July/August 2007 - 33
Engineering Inc. - July/August 2007 - 34
Engineering Inc. - July/August 2007 - 35
Engineering Inc. - July/August 2007 - 2007-2008 Excom
Engineering Inc. - July/August 2007 - 37
Engineering Inc. - July/August 2007 - 2007 Fall Conference Primer
Engineering Inc. - July/August 2007 - 39
Engineering Inc. - July/August 2007 - Business Insights
Engineering Inc. - July/August 2007 - 41
Engineering Inc. - July/August 2007 - Technology
Engineering Inc. - July/August 2007 - Members in the News
Engineering Inc. - July/August 2007 - 44
Engineering Inc. - July/August 2007 - 45
Engineering Inc. - July/August 2007 - 46
Engineering Inc. - July/August 2007 - 47
Engineering Inc. - July/August 2007 - One on One
Engineering Inc. - July/August 2007 - Cover3
Engineering Inc. - July/August 2007 - Cover4
https://www.nxtbook.com/nxtbooks/acec/engineeringinc_spring2020
https://www.nxtbook.com/nxtbooks/acec/engineeringinc_winter2020
https://www.nxtbook.com/nxtbooks/acec/engineeringinc1119
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0919
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0719
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0519
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0319
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0119
https://www.nxtbook.com/nxtbooks/acec/engineeringinc1118
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0918
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0718
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0518
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0318
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0118
https://www.nxtbook.com/nxtbooks/acec/engineeringinc1117
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0917
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0717
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0517
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0317
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0117
https://www.nxtbook.com/nxtbooks/acec/engineeringinc1116
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0916
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0716
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0516
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0316
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0116
https://www.nxtbook.com/nxtbooks/acec/engineeringinc1115
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0915
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0715
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0515
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0315
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0115
https://www.nxtbook.com/nxtbooks/acec/engineeringinc1114
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0914
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0714
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0514
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0314
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0114
https://www.nxtbook.com/nxtbooks/acec/engineeringinc1113
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0913
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0713
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0513
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0313
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0113
https://www.nxtbook.com/nxtbooks/acec/engineeringinc1112
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0912
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0712
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0512
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0312
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0112
https://www.nxtbook.com/nxtbooks/acec/engineeringinc1111
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0911
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0711
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0511
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0311
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0111
https://www.nxtbook.com/nxtbooks/acec/engineeringinc1110
https://www.nxtbook.com/nxtbooks/acec/engineeringincSeptOct
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0910
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0710
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0510
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0310
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0110
https://www.nxtbook.com/nxtbooks/acec/engineeringinc1109
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0909
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0709
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0309
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0109_v2
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0109
https://www.nxtbook.com/nxtbooks/acec/engineeringinc1108
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0908
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0708
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0508
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0308
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0108
https://www.nxtbook.com/nxtbooks/acec/engineeringinc1107
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0907
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0707
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0507
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0307
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0107
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0505
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0305
https://www.nxtbook.com/nxtbooks/acec/engineeringinc1105
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0306
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0105
https://www.nxtbook.com/nxtbooks/acec/engineeringinc1103
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0906
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0903
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0703
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0106
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0506
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0503
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0303
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0904
https://www.nxtbook.com/nxtbooks/acec/engineeringinc1104
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0704
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0504
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0304
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0905
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0705
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0104
https://www.nxtbook.com/nxtbooks/acec/engineeringinc1106
https://www.nxtbook.com/nxtbooks/acec/engineeringinc0706
https://www.nxtbookmedia.com