COLUMN ENGINEER'S NOTEBOOK

team can participate with all performance and pricing
data fully transparent. This information is collected by
requesting equipment bids from manufacturers' reps
using a bid form that includes performance data as well
as a final fixed price. The design and construction team
can then transparently discuss and weigh the advantages and disadvantages of each bid option, including
price, energy performance, noise, space requirements
etc., and make a final selection.
This approach is effective for selecting any equipment,
but it is ideal where any of the following is true:
* The specified product is unique, especially if it can
be bundled with other products.
* There are many different features among the available manufacturers that cannot be easily evaluated
without knowing and weighing the costs.
* There are significant variations in performance vs.
price so arbitrarily setting a single design performance
in bid documents may not result in the best selection.
* Other considerations where a side-by-side comparison makes for a better selection than low bid.
Examples include chillers, boilers, custom air handlers, and large packaged air-conditioning units.
The procedure can be implemented in one of two
ways, either during the design phase or after the design
is complete.

Design Phase Selection

Selecting equipment during the design phase is the
recommended option since it allows the design team to
design around equipment selections without concern
about redesigns that might be necessary if the contractor proposes substitutions. The bid should occur
when equipment capacities are known and relatively
firm, typically right at the start of the Construction
Documents (CD) phase. Here is a summary:
1. Decide which equipment will be bid using this
approach.
2. Prepare equipment specifications, as with any
project. In general, the specs should not mandate specific performance, such as chiller efficiency. Efficiency
will be evaluated later along with other selection criteria. However, it is desirable to specify maximum sound
power levels since there are multiple ways to address
sound, as discussed in the air-handler selection example
below.
3. Prepare a bid form for each equipment type. The

form must include price and performance data and
should include other application data such as power
requirements, weights, delivery information, etc. Two
examples, chiller selection and custom air-handling
unit selection, are discussed below.
4. Send the specs and bid forms to selected manufacturers' reps with a fixed bid period, typically two
weeks. The specs and forms usually include alternates
to either delete or add features the design team wants to
consider. Voluntary alternates from the bidders should
be encouraged. For large chillers, which are custom
equipment with an extremely wide range of price and
performance, bidders should be encouraged to make
multiple proposals. If a consulting engineer conducts
the bid, it is essential to make it clear that this bid is the
only bid for this equipment; there will be no opportunity
to rebid when the project is released for general contractor bidding. Reps who are not experienced with this process may consider this a "budget" and not provide competitive pricing, mistakenly thinking there will be an
opportunity later to provide the "real bid" to contractors.
It must be made clear that this is the "real bid." Also,
bidders should be allowed to deviate from the specifications in any way provided the deviations are spelled out
in the bid form. This ensures that the selection process
is not skewed to any one product. Deviations from the
specs are considered during the bid evaluation, just like
any other selection consideration.
5. Adjust pricing if there are secondary cost impacts of some options. For example, open-drive chillers require that a fan-coil be added in the chiller room
due to motor heat gain. As another example, most low
mass boilers require a minimum flow bypass while a
higher mass boiler may not. Note that cost is only one
consideration so these adjustments may be rough order
of magnitude estimates (ROMs) provided by the project
estimator.
6. Collect the bids and compile into a single table to
allow side-by-side comparison of the various features.
Usually, the engineer also provides additional subjective
information in the table, such as relative maintenance
costs, prior experience with each product or manufacturer, etc.
7. Meet with all team members who care to participate to discuss the bids and make a selection. On
a p&s project where contractors are not yet on board,
the meeting would typically be just the engineer and
D E C E M B E R 2 0 19

ashrae.org

ASHRAE JOURNAL

55


http://www.ashrae.org

ASHRAE Journal - December 2019

Table of Contents for the Digital Edition of ASHRAE Journal - December 2019

Contents
ASHRAE Journal - December 2019 - Intro
ASHRAE Journal - December 2019 - CT1
ASHRAE Journal - December 2019 - CT2
ASHRAE Journal - December 2019 - Cover1
ASHRAE Journal - December 2019 - Cover2
ASHRAE Journal - December 2019 - 1
ASHRAE Journal - December 2019 - Contents
ASHRAE Journal - December 2019 - 3
ASHRAE Journal - December 2019 - 4
ASHRAE Journal - December 2019 - 5
ASHRAE Journal - December 2019 - 6
ASHRAE Journal - December 2019 - 7
ASHRAE Journal - December 2019 - 8
ASHRAE Journal - December 2019 - 9
ASHRAE Journal - December 2019 - 10
ASHRAE Journal - December 2019 - 11
ASHRAE Journal - December 2019 - 12
ASHRAE Journal - December 2019 - 13
ASHRAE Journal - December 2019 - 14
ASHRAE Journal - December 2019 - 15
ASHRAE Journal - December 2019 - 16
ASHRAE Journal - December 2019 - 17
ASHRAE Journal - December 2019 - 18
ASHRAE Journal - December 2019 - 19
ASHRAE Journal - December 2019 - 20
ASHRAE Journal - December 2019 - 21
ASHRAE Journal - December 2019 - 22
ASHRAE Journal - December 2019 - 23
ASHRAE Journal - December 2019 - 24
ASHRAE Journal - December 2019 - 25
ASHRAE Journal - December 2019 - 26
ASHRAE Journal - December 2019 - 27
ASHRAE Journal - December 2019 - 28
ASHRAE Journal - December 2019 - 29
ASHRAE Journal - December 2019 - 30
ASHRAE Journal - December 2019 - 31
ASHRAE Journal - December 2019 - 32
ASHRAE Journal - December 2019 - 33
ASHRAE Journal - December 2019 - 34
ASHRAE Journal - December 2019 - 35
ASHRAE Journal - December 2019 - 36
ASHRAE Journal - December 2019 - 37
ASHRAE Journal - December 2019 - 38
ASHRAE Journal - December 2019 - 39
ASHRAE Journal - December 2019 - 40
ASHRAE Journal - December 2019 - 41
ASHRAE Journal - December 2019 - 42
ASHRAE Journal - December 2019 - 43
ASHRAE Journal - December 2019 - 44
ASHRAE Journal - December 2019 - 45
ASHRAE Journal - December 2019 - 46
ASHRAE Journal - December 2019 - 47
ASHRAE Journal - December 2019 - 48
ASHRAE Journal - December 2019 - 49
ASHRAE Journal - December 2019 - 50
ASHRAE Journal - December 2019 - 51
ASHRAE Journal - December 2019 - 52
ASHRAE Journal - December 2019 - 53
ASHRAE Journal - December 2019 - 54
ASHRAE Journal - December 2019 - 55
ASHRAE Journal - December 2019 - 56
ASHRAE Journal - December 2019 - 57
ASHRAE Journal - December 2019 - 58
ASHRAE Journal - December 2019 - 59
ASHRAE Journal - December 2019 - 60
ASHRAE Journal - December 2019 - 61
ASHRAE Journal - December 2019 - 62
ASHRAE Journal - December 2019 - 63
ASHRAE Journal - December 2019 - 64
ASHRAE Journal - December 2019 - 65
ASHRAE Journal - December 2019 - 66
ASHRAE Journal - December 2019 - 67
ASHRAE Journal - December 2019 - 68
ASHRAE Journal - December 2019 - 69
ASHRAE Journal - December 2019 - 70
ASHRAE Journal - December 2019 - 71
ASHRAE Journal - December 2019 - 72
ASHRAE Journal - December 2019 - 73
ASHRAE Journal - December 2019 - 74
ASHRAE Journal - December 2019 - 75
ASHRAE Journal - December 2019 - 76
ASHRAE Journal - December 2019 - 77
ASHRAE Journal - December 2019 - 78
ASHRAE Journal - December 2019 - 79
ASHRAE Journal - December 2019 - 80
ASHRAE Journal - December 2019 - 81
ASHRAE Journal - December 2019 - 82
ASHRAE Journal - December 2019 - 83
ASHRAE Journal - December 2019 - 84
ASHRAE Journal - December 2019 - 85
ASHRAE Journal - December 2019 - 86
ASHRAE Journal - December 2019 - 87
ASHRAE Journal - December 2019 - 88
ASHRAE Journal - December 2019 - 89
ASHRAE Journal - December 2019 - 90
ASHRAE Journal - December 2019 - 91
ASHRAE Journal - December 2019 - 92
ASHRAE Journal - December 2019 - 93
ASHRAE Journal - December 2019 - 94
ASHRAE Journal - December 2019 - 95
ASHRAE Journal - December 2019 - 96
ASHRAE Journal - December 2019 - 97
ASHRAE Journal - December 2019 - 98
ASHRAE Journal - December 2019 - 99
ASHRAE Journal - December 2019 - 100
ASHRAE Journal - December 2019 - 101
ASHRAE Journal - December 2019 - 102
ASHRAE Journal - December 2019 - 103
ASHRAE Journal - December 2019 - 104
ASHRAE Journal - December 2019 - 105
ASHRAE Journal - December 2019 - 106
ASHRAE Journal - December 2019 - 107
ASHRAE Journal - December 2019 - 108
ASHRAE Journal - December 2019 - 109
ASHRAE Journal - December 2019 - 110
ASHRAE Journal - December 2019 - 111
ASHRAE Journal - December 2019 - 112
ASHRAE Journal - December 2019 - 113
ASHRAE Journal - December 2019 - 114
ASHRAE Journal - December 2019 - 115
ASHRAE Journal - December 2019 - 116
ASHRAE Journal - December 2019 - 117
ASHRAE Journal - December 2019 - 118
ASHRAE Journal - December 2019 - 119
ASHRAE Journal - December 2019 - 120
ASHRAE Journal - December 2019 - 121
ASHRAE Journal - December 2019 - 122
ASHRAE Journal - December 2019 - 123
ASHRAE Journal - December 2019 - 124
ASHRAE Journal - December 2019 - 125
ASHRAE Journal - December 2019 - 126
ASHRAE Journal - December 2019 - 127
ASHRAE Journal - December 2019 - 128
ASHRAE Journal - December 2019 - 129
ASHRAE Journal - December 2019 - 130
ASHRAE Journal - December 2019 - 131
ASHRAE Journal - December 2019 - 132
ASHRAE Journal - December 2019 - 133
ASHRAE Journal - December 2019 - 134
ASHRAE Journal - December 2019 - 135
ASHRAE Journal - December 2019 - 136
ASHRAE Journal - December 2019 - Cover3
ASHRAE Journal - December 2019 - Cover4
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2024november_v2
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2024november
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_BDMHLG
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_WJDGRY
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_ATMAHK
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_VHQRAW
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_XGMDXI
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_YELQLJ
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_QJLWMC
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_MCDEBX
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_WNYSQY
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_XATVOD
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_FJSHSS
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_CCBZDS
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_XDEFVG
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2023november_v2
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2023november
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_VHGNBL
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_WPKBNJ
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_UUVCDE
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_RTGDEW
https://www.nxtbook.com/nxtbooks/ashrae/ashraemexico_2023
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_LKRFXS
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_AZSOFG
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_ERCDBH
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_QWDFRV
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_JHGVDF
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_OPUYHG
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_SREIBM
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_LRTGLK
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_OKRFGH
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2022november_v2
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2022november
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_TZSERA
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_LVRUIX
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_RPTVYZ
https://www.nxtbook.com/nxtbooks/ashrae/mini_pub_catalog
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_XIYTGD
https://www.nxtbook.com/nxtbooks/ashrae/ashraemexico_2022
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_RFGDOB
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_PABXNU
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_REMKLS
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_PICVBT
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_AOYTVW
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_JQOPLS
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_IOYTBC
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_SGAJJF
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_IGHYER
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_PDRKLS
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2021november
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2021november_v2
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_XCODFR
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_QSLFGO
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_ILKVNM
https://www.nxtbook.com/nxtbooks/ashrae/ashraemexico_2021
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_OPDJKD
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_VJKSRY
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_SDHUTC
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_JPPKRR
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_SDLTTH
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_CKLLES
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_SLDOX
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_HJETUK
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_OLUHGE
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2020october
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2020october_v2
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_ZERDGH
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_QVMNEO
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_RTPOKE
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_BBATRE
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_STUBMW
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_TPEMPE
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_JNMKDS
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_FBTTPA
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_WQMMNE
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_TVBRYN
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_showguide2020
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_KTUZMA
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_ABEDGD
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_201910
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_201909
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2019septmeber_v2
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2019september
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_201908
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_201907
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_201906
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_201905
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_201904
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_2019april
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_201903
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_2019march
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_201902
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_201901
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_showguide2019
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_2018december
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_2018november
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2018fall_v2
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2018fall
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_2018october
https://www.nxtbook.com/nxtbooks/ashrae/ashraemexico_2018
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201810
https://www.nxtbook.com/nxtbooks/ashrae/ashraeinsights_201806
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201805
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201804
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201803
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201712
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201711
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201710
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2017fall_v2
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2017fall
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201709
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201705
https://www.nxtbook.com/nxtbooks/ashrae/ashrae_meetinginsert_201610
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2016fall_v2
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2016fall
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_acrexindia
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2015summer_v2
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_amca_2015summer
https://www.nxtbook.com/nxtbooks/amca/2014summer2
https://www.nxtbook.com/nxtbooks/amca/2014summer
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_acma_2014summer
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201311
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201309
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_acmasupp_2013fall
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201305
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201303
https://www.nxtbook.com/nxtbooks/ashrae/pubcatalog_2013winter
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201211
https://www.nxtbook.com/nxtbooks/ashrae/achr_expo_mexico2012
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201209
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_201208_v3
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_201208_v2
https://www.nxtbook.com/nxtbooks/ashrae/pubcatalog_2012summer
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201205
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201203
https://www.nxtbook.com/nxtbooks/ashrae/pubcatalog_2012winter
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_201111_v2
https://www.nxtbook.com/nxtbooks/ashrae/ashraejournal_201109_v2
https://www.nxtbook.com/nxtbooks/ashrae/pubcatalog_2011summer
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201105
https://www.nxtbook.com/nxtbooks/ashrae/meetingplanner_201103
https://www.nxtbookmedia.com