Pipe produced by capable, reputable
mills that is based on applicable codes
and specifications should be subject to
factual evaluation. The mill's experience
in the production of each type of pipe
must be requested and validated.
Comparison of ERW and DSAW/LSAW pipes. The author
believes there is no general single option for pipe type (i.e.,
ERW vs. DSAW/LSAW) for use in large (> 16 nominal pipe
size, or NPS) onshore gas pipelines that is correct and applicable
for every application. Detailed study is needed based on
the project constrains (i.e., costs, schedule, etc.), pipeline terrain,
pipe specifications (e.g., grade, thickness, etc.), quality requirements,
risks, pipe manufacturer's experience, client's pipe
integrity experience, etc.
TABLE 1 gives a general comparison between ERW and
DSAW/LSAW pipes for sizes above 16 in. onshore buried gas
pipelines, based on the author's experience.
Proposed selection criteria. The selection between ERW
and DSAW/LSAW pipes in a pipeline project requires detailed
study, especially with regard to the mill's capability and experience.
The author proposes the following steps for making a
decision between ERW and DSAW/LSAW pipes:
1. Finalize critical operating and design parameters of the
pipeline system, such as pressure, temperature, flowrate,
minimum design metal temperature (MDMT), etc.
2. Conduct a reliable fracture control analysis based on
the rich gas composition of the gas. The Battelle TwoCurve
Method is a classic method that may be used.
3. Finalize the pipe grade, toughness and MDMT.
4. List the project constrains, including costs, schedule,
quality, resources, risks, customer experience and
preference, etc.
5. Conduct a market study and identify and manage
the associated risks.
6. Decide on potential mills for the pipe manufacture
and request their workload, past experience,
production processes for different types of pipe,
optional tests and inspections, etc.
7. Determine the evaluating parameters and
associated weights.
8. Prepare a pipe datasheet based on two options
(ERW and DSAW/LSAW) and send the datasheet
with a material requisition to the potential mills.
9. As part of the quote for supply of line pipe, ask the
manufacturer to submit a manufacturing procedure
specification (MPS) document providing information
on raw material, production process, inspection,
test, etc. in detail.
10. Review the mill's quote and prepare technical and
commercial evaluations in a bias-free atmosphere.
Clarify unclear areas with the mills and a subject
matter expert.
18 MAY/JUNE 2021 | GasProcessingNews.com
11. Consider a brainstorming session and ask for feedback
from construction, the pipeline integrity team,
shop inspectors, etc.
12. Conduct a cost-benefit analysis by considering
the cost of risk and all key factors, rather than just
the pipe cost quoted by the mills.
Recommendations. Many factors and risks must be considered
in the selection of the final pipe type (between ERW and
DSAW/LSAW) for an onshore buried natural gas pipeline
project, based on the actual project requirements and conditions.
The project manager should ensure that a bias-free engineering
study has been conducted.
The author's conclusion is that for a pipe size of 16
in.-26 in., both ERW and SAW pipes are possible options for
an onshore buried natural gas pipeline project. A final decision
must be made based on a detailed study considering many factors
besides the pipe cost. If a pipe longitudinal fails during
operation, then the root causes, direct causes and contributing
causes must be discerned.
The author believes that pipe produced by capable, reputable
mills that is based on applicable codes, standards and
specifications should be subject to factual evaluation and not
personal judgment. The mill's experience in the production of
each type of pipe in similar service, thickness, size and grade
must be requested and validated. Engineers must ask for manufacturing
procedure qualification testing (MPQT), manufacturing
procedure specifications (MPS) and other standards.
Finally, continual advances
in materials and welding
techniques have resulted in dramatic improvements in the
reliability of both ERW and DSAW/LSAW pipes. For highpressure
applications with design pressure of ≥ 100 barg, the
author prefers DSAW/LSAW pipes, as discussed in the last
row of TABLE 1.
Regardless of which type is selected, the risks of corrosion,
fatigue and seam-related defects to the longitudinal weld
seams of ERW and DSAW/LSAW pipes still exist. These defects
should be monitored and identified through integrity
assessments (e.g., hydrostatic tests, indirect assessments and
direct assessments) and must be repaired when found. GP
LITERATURE CITED
1
2
Limon, S. and D. Katz, " A ERW seam weld failure, " Paper No. 08150, NACE
International Corrosion Conference and Expo, 2008.
U.S. National Transportation Safety Board, " Pipeline accident report: Rupture of
Enbridge Pipeline and release of crude oil near Cohasset, Minnesota, July 4, 2002 "
NTSB/PAR-04/01, June 23, 2004.
3 JFE Steel Corp., Line Pipe Catalog No. E1E-001-05.
4
1, 2011, Online:
FSPipeManufacturingProcess.htm
5 JFE Steel Corp., Technical Report No. 18, March 2013.
SHAHAB ZARDYNEZHAD is a registered senior mechanical/
pipeline engineer in Alberta with more than 29 yr of experience
working in the world's largest oil, gas and petrochemical
projects. He has experience in many cross-country, longdistance
pipeline projects including buried, aboveground,
thermal, high-pressure, NGL and sour gas pipelines. He holds a
BS degree in mechanical engineering from the University of
Petroleum of Iran, an MS degree in industrial engineering from IUST Iran and MS
degrees in project management and mechanical engineering (pipeline
specialization) from the University of Calgary in Canada.
U.S. Department of Transportation, Pipeline & Hazardous Materials Safety
Administration,
" Fact sheet: Pipe manufacturing process, " December
https://primis.phmsa.dot.gov/comm/FactSheets/
https://primis.phmsa.dot.gov/comm/FactSheets/FSPipeManufacturingProcess.htm https://primis.phmsa.dot.gov/comm/FactSheets/FSPipeManufacturingProcess.htm http://www.GasProcessingNews.com

Hydrocarbon Processing - June 2021

Table of Contents for the Digital Edition of Hydrocarbon Processing - June 2021

Contents
Hydrocarbon Processing - June 2021 - Cover1
Hydrocarbon Processing - June 2021 - Cover2
Hydrocarbon Processing - June 2021 - Contents
Hydrocarbon Processing - June 2021 - 4
Hydrocarbon Processing - June 2021 - 5
Hydrocarbon Processing - June 2021 - 6
Hydrocarbon Processing - June 2021 - 7
Hydrocarbon Processing - June 2021 - 8
Hydrocarbon Processing - June 2021 - 9
Hydrocarbon Processing - June 2021 - 10
Hydrocarbon Processing - June 2021 - 11
Hydrocarbon Processing - June 2021 - 12
Hydrocarbon Processing - June 2021 - 13
Hydrocarbon Processing - June 2021 - 14
Hydrocarbon Processing - June 2021 - 15
Hydrocarbon Processing - June 2021 - 16
Hydrocarbon Processing - June 2021 - 17
Hydrocarbon Processing - June 2021 - 18
Hydrocarbon Processing - June 2021 - 19
Hydrocarbon Processing - June 2021 - 20
Hydrocarbon Processing - June 2021 - 21
Hydrocarbon Processing - June 2021 - 22
Hydrocarbon Processing - June 2021 - 23
Hydrocarbon Processing - June 2021 - 24
Hydrocarbon Processing - June 2021 - 25
Hydrocarbon Processing - June 2021 - 26
Hydrocarbon Processing - June 2021 - 27
Hydrocarbon Processing - June 2021 - 28
Hydrocarbon Processing - June 2021 - 29
Hydrocarbon Processing - June 2021 - 30
Hydrocarbon Processing - June 2021 - 31
Hydrocarbon Processing - June 2021 - 32
Hydrocarbon Processing - June 2021 - 33
Hydrocarbon Processing - June 2021 - 34
Hydrocarbon Processing - June 2021 - 35
Hydrocarbon Processing - June 2021 - 36
Hydrocarbon Processing - June 2021 - 37
Hydrocarbon Processing - June 2021 - 38
Hydrocarbon Processing - June 2021 - 39
Hydrocarbon Processing - June 2021 - 40
Hydrocarbon Processing - June 2021 - 41
Hydrocarbon Processing - June 2021 - 42
Hydrocarbon Processing - June 2021 - 43
Hydrocarbon Processing - June 2021 - 44
Hydrocarbon Processing - June 2021 - 45
Hydrocarbon Processing - June 2021 - 46
Hydrocarbon Processing - June 2021 - 47
Hydrocarbon Processing - June 2021 - 48
Hydrocarbon Processing - June 2021 - 49
Hydrocarbon Processing - June 2021 - 50
Hydrocarbon Processing - June 2021 - 51
Hydrocarbon Processing - June 2021 - 52
Hydrocarbon Processing - June 2021 - 53
Hydrocarbon Processing - June 2021 - 54
Hydrocarbon Processing - June 2021 - 55
Hydrocarbon Processing - June 2021 - 56
Hydrocarbon Processing - June 2021 - 57
Hydrocarbon Processing - June 2021 - 58
Hydrocarbon Processing - June 2021 - 59
Hydrocarbon Processing - June 2021 - 60
Hydrocarbon Processing - June 2021 - 61
Hydrocarbon Processing - June 2021 - 62
Hydrocarbon Processing - June 2021 - 63
Hydrocarbon Processing - June 2021 - 64
Hydrocarbon Processing - June 2021 - 65
Hydrocarbon Processing - June 2021 - 66
Hydrocarbon Processing - June 2021 - 67
Hydrocarbon Processing - June 2021 - 68
Hydrocarbon Processing - June 2021 - 69
Hydrocarbon Processing - June 2021 - 70
Hydrocarbon Processing - June 2021 - 71
Hydrocarbon Processing - June 2021 - 72
Hydrocarbon Processing - June 2021 - 73
Hydrocarbon Processing - June 2021 - 74
Hydrocarbon Processing - June 2021 - 75
Hydrocarbon Processing - June 2021 - 76
Hydrocarbon Processing - June 2021 - 77
Hydrocarbon Processing - June 2021 - 78
Hydrocarbon Processing - June 2021 - 79
Hydrocarbon Processing - June 2021 - 80
Hydrocarbon Processing - June 2021 - 81
Hydrocarbon Processing - June 2021 - 82
Hydrocarbon Processing - June 2021 - 83
Hydrocarbon Processing - June 2021 - 84
Hydrocarbon Processing - June 2021 - 85
Hydrocarbon Processing - June 2021 - 86
Hydrocarbon Processing - June 2021 - 87
Hydrocarbon Processing - June 2021 - 88
Hydrocarbon Processing - June 2021 - 89
Hydrocarbon Processing - June 2021 - 90
Hydrocarbon Processing - June 2021 - Cover3
Hydrocarbon Processing - June 2021 - Cover4
Hydrocarbon Processing - June 2021 - GP-1
Hydrocarbon Processing - June 2021 - GP-2
Hydrocarbon Processing - June 2021 - GP-3
Hydrocarbon Processing - June 2021 - GP-4
Hydrocarbon Processing - June 2021 - GP-5
Hydrocarbon Processing - June 2021 - GP-6
Hydrocarbon Processing - June 2021 - GP-7
Hydrocarbon Processing - June 2021 - GP-8
Hydrocarbon Processing - June 2021 - GP-9
Hydrocarbon Processing - June 2021 - GP-10
Hydrocarbon Processing - June 2021 - GP-11
Hydrocarbon Processing - June 2021 - GP-12
Hydrocarbon Processing - June 2021 - GP-13
Hydrocarbon Processing - June 2021 - GP-14
Hydrocarbon Processing - June 2021 - GP-15
Hydrocarbon Processing - June 2021 - GP-16
Hydrocarbon Processing - June 2021 - GP-17
Hydrocarbon Processing - June 2021 - GP-18
Hydrocarbon Processing - June 2021 - GP-19
Hydrocarbon Processing - June 2021 - GP-20
Hydrocarbon Processing - June 2021 - GP-21
Hydrocarbon Processing - June 2021 - GP-22
Hydrocarbon Processing - June 2021 - GP-23
Hydrocarbon Processing - June 2021 - GP-24
Hydrocarbon Processing - June 2021 - GP-25
Hydrocarbon Processing - June 2021 - GP-26
Hydrocarbon Processing - June 2021 - GP-27
Hydrocarbon Processing - June 2021 - GP-28
Hydrocarbon Processing - June 2021 - GP-29
Hydrocarbon Processing - June 2021 - GP-30
Hydrocarbon Processing - June 2021 - GP-31
Hydrocarbon Processing - June 2021 - GP-32
Hydrocarbon Processing - June 2021 - GP-33
Hydrocarbon Processing - June 2021 - GP-34
Hydrocarbon Processing - June 2021 - GP-35
Hydrocarbon Processing - June 2021 - GP-36
Hydrocarbon Processing - June 2021 - GP-37
Hydrocarbon Processing - June 2021 - GP-38
Hydrocarbon Processing - June 2021 - GP-39
Hydrocarbon Processing - June 2021 - GP-40
Hydrocarbon Processing - June 2021 - GP-41
Hydrocarbon Processing - June 2021 - GP-42
Hydrocarbon Processing - June 2021 - GP-43
Hydrocarbon Processing - June 2021 - GP-44
https://www.nxtbook.com/gulfenergyinfo/gulfpub/hpi-market-data-2025
https://www.nxtbook.com/gulfenergyinfo/gulfpub/HPI-Market-Data-2023-v3
https://www.nxtbook.com/gulfenergyinfo/gulfpub/hpi-market-data-2024-v2
https://www.nxtbook.com/gulfenergyinfo/gulfpub/hpi-market-data-2024
https://www.nxtbook.com/gulfenergyinfo/gulfpub/gas-processes-handbook-2022_v2
https://www.nxtbook.com/gulfenergyinfo/gulfpub/gas-processes-handbook-2022
https://www.nxtbook.com/gulfenergyinfo/gulfpub/hp_202212
https://www.nxtbook.com/gulfenergyinfo/gulfpub/hpi-market-data-2023-v2
https://www.nxtbook.com/gulfenergyinfo/gulfpub/hpi-market-data-2023
https://www.nxtbook.com/gulfenergyinfo/gulfpub/hp_202211
https://www.nxtbook.com/nxtbooks/gulfpub/hp_202210
https://www.nxtbook.com/nxtbooks/gulfpub/hp_202209
https://www.nxtbook.com/nxtbooks/gulfpub/hp_202208
https://www.nxtbook.com/nxtbooks/gulfpub/hp_202207_v2
https://www.nxtbook.com/nxtbooks/gulfpub/hp_202207
https://www.nxtbook.com/nxtbooks/gulfpub/hp_202206_v2
https://www.nxtbook.com/nxtbooks/gulfpub/hp_202206
https://www.nxtbook.com/nxtbooks/gulfpub/hp_202205_v2
https://www.nxtbook.com/nxtbooks/gulfpub/hp_202205
https://www.nxtbook.com/nxtbooks/gulfpub/hp_202204_v2
https://www.nxtbook.com/nxtbooks/gulfpub/hp_202204
https://www.nxtbook.com/nxtbooks/gulfpub/hp_032022
https://www.nxtbook.com/nxtbooks/gulfpub/hp_202203
https://www.nxtbook.com/nxtbooks/gulfpub/hp_202202
https://www.nxtbook.com/nxtbooks/gulfpub/hp_202201
https://www.nxtbook.com/nxtbooks/gulfpub/hp_202112
https://www.nxtbook.com/nxtbooks/gulfpub/hp_202111
https://www.nxtbook.com/nxtbooks/gulfpub/hp_202110
https://www.nxtbook.com/nxtbooks/gulfpub/hpimarket_2022_v2
https://www.nxtbook.com/nxtbooks/gulfpub/hpimarket_2022
https://www.nxtbook.com/nxtbooks/gulfpub/hp_202109
https://www.nxtbook.com/nxtbooks/gulfpub/hp_202108
https://www.nxtbook.com/nxtbooks/gulfpub/petrochemical_processes_handbook_2021_v2
https://www.nxtbook.com/nxtbooks/gulfpub/petrochemical_processes_handbook_2021
https://www.nxtbook.com/nxtbooks/gulfpub/hp_202107
https://www.nxtbook.com/nxtbooks/gulfpub/hp_202106
https://www.nxtbook.com/nxtbooks/gulfpub/hp_202105
https://www.nxtbook.com/nxtbooks/gulfpub/hp_202104
https://www.nxtbook.com/nxtbooks/gulfpub/hp_ebooks
https://www.nxtbook.com/nxtbooks/gulfpub/hp_202103
https://www.nxtbook.com/nxtbooks/gulfpub/hp_202102
https://www.nxtbook.com/nxtbooks/gulfpub/hp_202101
https://www.nxtbook.com/nxtbooks/gulfpub/catalyst_handbook_2020_v2
https://www.nxtbook.com/nxtbooks/gulfpub/catalyst_handbook_2020
https://www.nxtbook.com/nxtbooks/gulfpub/hp_202012
https://www.nxtbook.com/nxtbooks/gulfpub/hp_202011
https://www.nxtbook.com/nxtbooks/gulfpub/hp_202010
https://www.nxtbook.com/nxtbooks/gulfpub/hpimarket_2021
https://www.nxtbook.com/nxtbooks/gulfpub/hp_202009
https://www.nxtbook.com/nxtbooks/gulfpub/hp_202008
https://www.nxtbook.com/nxtbooks/gulfpub/refining_processes_handbook_2020
https://www.nxtbook.com/nxtbooks/gulfpub/refining_processes_handbook_2020_v2
https://www.nxtbook.com/nxtbooks/gulfpub/hp_202007
https://www.nxtbook.com/nxtbooks/gulfpub/hp_202006
https://www.nxtbook.com/nxtbooks/gulfpub/hp_202005
https://www.nxtbook.com/nxtbooks/gulfpub/hp_202004
https://www.nxtbook.com/nxtbooks/gulfpub/hp_202003
https://www.nxtbook.com/nxtbooks/gulfpub/hp_202002
https://www.nxtbook.com/nxtbooks/gulfpub/hp_202001
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201912
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201911
https://www.nxtbook.com/nxtbooks/gulfpub/hpimarket_2020_v2
https://www.nxtbook.com/nxtbooks/gulfpub/hpimarket_2020
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201910
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201909
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201908
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201907
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201906
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201905
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201904
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201903
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201902
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201901
https://www.nxtbook.com/nxtbooks/gulfpub/petrochemical_2018_v2
https://www.nxtbook.com/nxtbooks/gulfpub/petrochemical_2018
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201812
https://www.nxtbook.com/nxtbooks/gulfpub/hpimarket_2019_v2
https://www.nxtbook.com/nxtbooks/gulfpub/hpimarket_2019
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201811
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201810
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201809
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201808
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201807
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201806
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201805
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201804
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201803
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201802
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201801
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201712
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201711
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201710
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201709
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201708
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201707
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201706
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201705
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201704
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201703
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201702
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201701
https://www.nxtbook.com/nxtbooks/gulfpub/hp_2017mediaplanner
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201612
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201611
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201610
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201609
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201608
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201607
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201606
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201605
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201604
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201603
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201602
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201601
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201512
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201511
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201510
https://www.nxtbook.com/nxtbooks/gulfpub/hp_2016mediaplanner
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201509
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201508
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201507
https://www.nxtbook.com/nxtbooks/gulfpub/hp_2015tmsd
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201506
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201505
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201504
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201503
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201502
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201501
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201412
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201411
https://www.nxtbook.com/nxtbooks/gulfpub/hp_2015mediaplanner
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201410
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201409
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201408
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201407
https://www.nxtbook.com/nxtbooks/gulfpub/hp_2014petrochemicalprocesses_v2
https://www.nxtbook.com/nxtbooks/gulfpub/hp_2014petrochemicalprocesses
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201406
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201405
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201404
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201403
https://www.nxtbook.com/nxtbooks/gulfpub/hp_2014calendar
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201402
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201401
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201312
https://www.nxtbook.com/nxtbooks/gulfpub/hp_2014mediaplanner
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201311
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201310
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201309
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201308
https://www.nxtbook.com/nxtbooks/gulfpub/hp_srsguide2013
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201307
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201306
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201305
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201304
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201303
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201302
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201301
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201212
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201211
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201210
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201209
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201208
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201207
https://www.nxtbook.com/nxtbooks/gulfpub/hp_srsguide2012
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201206
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201205
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201204
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201203
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201202
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201201
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201112
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201111
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201110
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201109
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201108
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201107_srsguide
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201107
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201106
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201105
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201104
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201103
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201102
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201101
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201012
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201011
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201010
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201009
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201008
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201007
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201006
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201005
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201004
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201003
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201002
https://www.nxtbook.com/nxtbooks/gulfpub/hp_201001
https://www.nxtbook.com/nxtbooks/gulfpub/hp_200912
https://www.nxtbook.com/nxtbooks/gulfpub/hp_200911
https://www.nxtbook.com/nxtbooks/gulfpub/hp_200910
https://www.nxtbook.com/nxtbooks/gulfpub/hp_200909
https://www.nxtbook.com/nxtbooks/gulfpub/hp_200908
https://www.nxtbook.com/nxtbooks/gulfpub/hp_200907
https://www.nxtbook.com/nxtbooks/gulfpub/hp_200906
https://www.nxtbook.com/nxtbooks/gulfpub/hp_200905
https://www.nxtbook.com/nxtbooks/gulfpub/hp_200904
https://www.nxtbook.com/nxtbooks/gulfpub/hp_200903
https://www.nxtbook.com/nxtbooks/gulfpub/hp_200902
https://www.nxtbook.com/nxtbooks/gulfpub/hp_200901
https://www.nxtbookmedia.com