Underground Construction - October 2017 - 36

20 17 C A PA B I LITI E S G U I D E
SPECIAL ADVERTISING SECTION

Hydraulic Excavation Brace Saves
Contractor Time and Money

A

A Central Florida contractor was performing one portion of a water expansion project that would require a bore beneath existing rail tracks.
The contractor estimated the excavation would need to be about 40-ft
long, 16-ft wide and about 19-ft deep to provide the necessary room to
operate the boring machine and complete the work. The contractor's
competent person had classified the clay and brown sand mixture as a
Type C-60 soil.
The contractor had identified several requirements that an eventual
shoring system would need to address. The excavation site would feature two fiber optic lines that would traverse the excavation at different
depths. The bore pit would be located within 25-ft of the railroad tracks,
while the receiving pit would be within 10-ft of an active roadway and
within 50-ft of a retention pond. The contractor and rail authority would
be monitoring the tracks to ensure that there was no sinking of the
tracks as a result of the project work.
The contractor called NTS to discuss shoring options for the project.
In this area of Florida, this type of excavation would typically feature
slide rail shoring or sheeting to provide positive soil support throughout the excavation process given the proximity to a roadway and the rail

36

ucononline.com

tracks. The fiber optic lines presented an issue that would require flexible
placement along the site to ensure that the fiber optic lines weren't damaged during excavation. The contractor elected to use steel sheeting with
hydraulic bracing to shore the project, as the sheeting could be installed
around the fiber optic lines, while wood lagging could be used to fill the
associated gaps. Hydraulic bracing was chosen due to its strength and
efficient installation process. If the contractor had elected to use welded
in place beam walers, the contractor had estimated that process would
have taken about a week to weld the beams. Using the hydraulic bracing,
the contractor was able to install the sheeting and set the hydraulic bracing quickly to advance the project schedule.
The combination of sheeting and hydraulic bracing provided positive
soil support throughout the excavation and helped to prevent any soil
raveling that could have led to the road or train tracks being undermined. The system was site specific engineered to ensure compliance
and was presented to the rail authority as well as department of transportation beforehand for review and approval.
The contractor was extremely satisfied with the system's performance
and the time and cost savings its use generated.

Underground Construction October 2017


http://www.ucononline.com

Underground Construction - October 2017

Table of Contents for the Digital Edition of Underground Construction - October 2017

Underground Construction - October 2017
Contents
Editor’s Log
Newsline
Washington Watch
Pipeline Projects
2017 Capabilities Guide
Vic Weston named 2018 MVP
Utility & Communications Construction Business Update
Family, Customer Values Fuel Growth Of CMW
Pipe Bursting: What Are The Technology Expectations?
Bursting In Grand Prairie
NASSCO Tech Tips: The Importance Of Proper Nozzle Selection
Products: Pipe Bursting/Trenchless Pipe Replacement
Business
New Products
Equipment Spotlight
Business Cards
Ad Index
Sales Reps
Calendar Of Events
The Last Word: NASSCO’s Response To Purdue University’s Findings On CIPP
Underground Construction - October 2017 - Underground Construction - October 2017
Underground Construction - October 2017 - IFC
Underground Construction - October 2017 - Contents
Underground Construction - October 2017 - Editor’s Log
Underground Construction - October 2017 - 3
Underground Construction - October 2017 - Newsline
Underground Construction - October 2017 - 5
Underground Construction - October 2017 - 6
Underground Construction - October 2017 - 7
Underground Construction - October 2017 - Washington Watch
Underground Construction - October 2017 - 9
Underground Construction - October 2017 - Pipeline Projects
Underground Construction - October 2017 - 11
Underground Construction - October 2017 - 2017 Capabilities Guide
Underground Construction - October 2017 - 13
Underground Construction - October 2017 - 14
Underground Construction - October 2017 - 15
Underground Construction - October 2017 - 16
Underground Construction - October 2017 - 17
Underground Construction - October 2017 - 18
Underground Construction - October 2017 - 19
Underground Construction - October 2017 - 20
Underground Construction - October 2017 - 21
Underground Construction - October 2017 - 22
Underground Construction - October 2017 - 23
Underground Construction - October 2017 - 24
Underground Construction - October 2017 - 25
Underground Construction - October 2017 - 26
Underground Construction - October 2017 - 27
Underground Construction - October 2017 - 28
Underground Construction - October 2017 - 29
Underground Construction - October 2017 - 30
Underground Construction - October 2017 - 31
Underground Construction - October 2017 - 32
Underground Construction - October 2017 - 33
Underground Construction - October 2017 - 34
Underground Construction - October 2017 - 35
Underground Construction - October 2017 - 36
Underground Construction - October 2017 - 37
Underground Construction - October 2017 - 38
Underground Construction - October 2017 - 39
Underground Construction - October 2017 - 40
Underground Construction - October 2017 - 41
Underground Construction - October 2017 - 42
Underground Construction - October 2017 - 43
Underground Construction - October 2017 - 44
Underground Construction - October 2017 - Vic Weston named 2018 MVP
Underground Construction - October 2017 - Utility & Communications Construction Business Update
Underground Construction - October 2017 - 47
Underground Construction - October 2017 - Family, Customer Values Fuel Growth Of CMW
Underground Construction - October 2017 - 49
Underground Construction - October 2017 - 50
Underground Construction - October 2017 - 51
Underground Construction - October 2017 - Pipe Bursting: What Are The Technology Expectations?
Underground Construction - October 2017 - 53
Underground Construction - October 2017 - Bursting In Grand Prairie
Underground Construction - October 2017 - 55
Underground Construction - October 2017 - NASSCO Tech Tips: The Importance Of Proper Nozzle Selection
Underground Construction - October 2017 - 57
Underground Construction - October 2017 - Products: Pipe Bursting/Trenchless Pipe Replacement
Underground Construction - October 2017 - Business
Underground Construction - October 2017 - 60
Underground Construction - October 2017 - 61
Underground Construction - October 2017 - New Products
Underground Construction - October 2017 - 63
Underground Construction - October 2017 - 64
Underground Construction - October 2017 - 65
Underground Construction - October 2017 - Equipment Spotlight
Underground Construction - October 2017 - Business Cards
Underground Construction - October 2017 - 68
Underground Construction - October 2017 - 69
Underground Construction - October 2017 - 70
Underground Construction - October 2017 - Calendar Of Events
Underground Construction - October 2017 - The Last Word: NASSCO’s Response To Purdue University’s Findings On CIPP
Underground Construction - October 2017 - IBC
Underground Construction - October 2017 - BC
Underground Construction - October 2017 - UCTFC
Underground Construction - October 2017 - UCTIFC
Underground Construction - October 2017 - UCT1
Underground Construction - October 2017 - UCT2
Underground Construction - October 2017 - UCT3
Underground Construction - October 2017 - UCT4
Underground Construction - October 2017 - UCT5
Underground Construction - October 2017 - UCT6
Underground Construction - October 2017 - UCT7
Underground Construction - October 2017 - UCT8
Underground Construction - October 2017 - UCT9
Underground Construction - October 2017 - UCT10
Underground Construction - October 2017 - UCT11
Underground Construction - October 2017 - UCT12
Underground Construction - October 2017 - UCT13
Underground Construction - October 2017 - UCT14
Underground Construction - October 2017 - UCT15
Underground Construction - October 2017 - UCT16
Underground Construction - October 2017 - UCT17
Underground Construction - October 2017 - UCT18
Underground Construction - October 2017 - UCT19
Underground Construction - October 2017 - UCT20
Underground Construction - October 2017 - UCT21
Underground Construction - October 2017 - UCT22
https://www.nxtbook.com/gulfenergyinfo/gulfpub/underground-construction-december-2022
https://www.nxtbook.com/gulfenergyinfo/gulfpub/uc_202211
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202210
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202209
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202208
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202207
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202206
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202205
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202204
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202203
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202202
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202201
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202112
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202111
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202110
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202109
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202108
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202107
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202106
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202105
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202104
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202103
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202102
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202101
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202012
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202011
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202010
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202009
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202008
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202007
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202006
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202005
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202004
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202003
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202002
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202001
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201912
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201911
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201910
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201909
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201908
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201907
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201906
https://www.nxtbook.com/nxtbooks/gulfpub/uesi_summer2019
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201905
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201904
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201903
https://www.nxtbook.com/nxtbooks/gulfpub/uesi_winter2019
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201902
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201901
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201812
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201811
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201810
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201809
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201808
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201807
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201806
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201805
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201804
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201803
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201802
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201801
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201712
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201711
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201710
https://www.nxtbook.com/nxtbooks/gulfpub/uc_ditchwitch
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201709
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201708
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201707
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201706
https://www.nxtbookmedia.com