Ancient Roman Construction Methods
Still Connect to Modern Pipeline Work
Joe Pikas | Technical ToolBoxes
It's interesting to note that it is easier to find ancient Roman
history documentation about its infrastructure system (i.e., all
roads lead to Rome), buildings, water/via-ducts and stadiums, than
find a document about a U.S. pipeline built within the last 50 years.
How are we to comply with the Protecting Our Infrastructure of
Pipelines and Enhancing Safety (PIPES) Act of 2020 Act?
I just read a great article in National Geographic on the ancient
Roman Roads linking that world to our reality. What interested
me at first glance was the groma (transit) that was used to build
roads and other infrastructures. It brought back memories of my
pipeline engineering construction days.
My first job with a large pipeline company was the 1966
construction of one of the first 42-inch pipelines in the U.S.,
located in New Jersey, near Washington's crossing on the
Delaware River, to Princeton and then to Morgan, N.J. Reading
the article, I realized the methods and instruments used on that
project were similar to the Romans' groma.
We used a K&E transit instrument, which is somewhat more
advanced than the Romans' use of poles for stakes and up to five
plum bobs for alignment. Their " telescope " consisted of pacing
back 100 steps and aligning the plum bobs. Conversely, we used
crosshairs in a scope and probably yelled out the same commands
to the guy who was putting in the stakes for alignment of the
pipeline, compared to their setting poles for alignment of roads or
other structures.
What is interesting is that the Romans used polla (stone)
tablets with inscriptions that date back to 132 BC, whereas we
used yellow-paper, field engineering survey books. You can say
that their data survived wars, fires and hackers over the years,
compared to our common paper. I would even say that their data
Technical Toolboxes
Technical Toolboxes provide integrated desktop and cloud-based pipeline
engineering software, online resources, and specialized training for
pipeline engineering professionals around the world. The fit-for-purpose
pipeline engineering software platform we offer will help you reduce risk,
lower total cost of operations and accelerate project schedules.
As pipeline engineering professionals embrace digital change, Technical
Toolboxes' legacy applications are evolving, from manual calculators
into sophisticated, integrated holistic analysis tools that enable users to
make efficient, accurate decisions through a collaboration feature.
The recently released Pipeline HUBPL platform automates integration
and analyses for insights into infrastructure design and operational fitness.
It connects a library of engineering standards and tools to users' data
across a pipeline lifecycle. Integrated maps allow geospatial analysis,
visual reconnaissance of existing databases and leveraging of disparate
GIS data components.
24 NOVEMBER 2021 | UCONonline.com
could survive a PHMSA audit and be traceable, verifiable, and
completely compliant with little or no problems.
Pipeline engineering construction procedures
The procedures for determining how, when and where a pipeline
is constructed is more complex today than the earlier, 1950s and
'60s installations.
Preliminary planning and route selection, including rightof-way
acquisition, is more restricted. A good example is when
pipeline operators are restricted to stay within the power line and
other rights of way to minimize costs.
Pipeline design now requires more HDD crossings, due to
environmentally sensitive areas like wet-lands and other water
bodies. This also includes crossings of roads, railroads and other
(foreign) pipelines.
There are many phases and details of pipeline construction,
including:
* Clearing and grading
* Unloading, hauling, storing and stringing of pipe
* Ditching, bending, welding, lowering and laying pipe
* Determination of open cut, jack bore, HDD crossings
* Line pipe coatings, field joints and tie-in welds
* Valves, isolating flanges, taps, test leads and cathodic protection
* Cleanup and restoration
* Hydro testing and revenue operations
It should be noted that pipeline construction does not include
compressor, pump, meter station and related facilities. These
are considered separate construction engineering projects. In
addition, pipe manufacturing (mill) and coating applications must
be done before any of these activities can begin.
Ancient Rome versus today
Not too much in the way of specifications has changed since the
ancient Romans. For example, here's the wording on a pipeline
construction specification:
Ditching
* Contractor shall dig the pipeline ditch at the designated offset
or on the staked line provided by company.
* When ditching across or adjacent to roads, highways, railroads,
ditches, etc. where extra ditching is required, contractor shall
at no additional cost, excavate the additional depth necessary
to meet the requirements of the company.
It is interesting to note that the Romans used a public bidding
process and private contractors were awarded projects, like
today's standards. They also used criminals for their laborers and
military engineers to design and supervise the work.
Similarly, many of the Roman roads were built for military
type of operations, not unlike the interstate highway system
that was originally built and started by President Eisenhower
http://www.UCONonline.com
Underground Construction - November 2021
Table of Contents for the Digital Edition of Underground Construction - November 2021
Contents
Underground Construction - November 2021 - Cover1
Underground Construction - November 2021 - Cover2
Underground Construction - November 2021 - Contents
Underground Construction - November 2021 - 4
Underground Construction - November 2021 - 5
Underground Construction - November 2021 - 6
Underground Construction - November 2021 - 7
Underground Construction - November 2021 - 8
Underground Construction - November 2021 - 9
Underground Construction - November 2021 - 10
Underground Construction - November 2021 - 11
Underground Construction - November 2021 - 12
Underground Construction - November 2021 - 13
Underground Construction - November 2021 - 14
Underground Construction - November 2021 - 15
Underground Construction - November 2021 - 16
Underground Construction - November 2021 - 17
Underground Construction - November 2021 - 18
Underground Construction - November 2021 - 19
Underground Construction - November 2021 - 20
Underground Construction - November 2021 - 21
Underground Construction - November 2021 - 22
Underground Construction - November 2021 - 23
Underground Construction - November 2021 - 24
Underground Construction - November 2021 - 25
Underground Construction - November 2021 - 26
Underground Construction - November 2021 - 27
Underground Construction - November 2021 - 28
Underground Construction - November 2021 - 29
Underground Construction - November 2021 - 30
Underground Construction - November 2021 - 31
Underground Construction - November 2021 - 32
Underground Construction - November 2021 - 33
Underground Construction - November 2021 - 34
Underground Construction - November 2021 - 35
Underground Construction - November 2021 - 36
Underground Construction - November 2021 - 37
Underground Construction - November 2021 - 38
Underground Construction - November 2021 - 39
Underground Construction - November 2021 - 40
Underground Construction - November 2021 - 41
Underground Construction - November 2021 - 42
Underground Construction - November 2021 - 43
Underground Construction - November 2021 - 44
Underground Construction - November 2021 - 45
Underground Construction - November 2021 - 46
Underground Construction - November 2021 - 47
Underground Construction - November 2021 - 48
Underground Construction - November 2021 - 49
Underground Construction - November 2021 - 50
Underground Construction - November 2021 - Cover3
Underground Construction - November 2021 - Cover4
Underground Construction - November 2021 - UCT1
Underground Construction - November 2021 - UCT2
Underground Construction - November 2021 - UCT3
Underground Construction - November 2021 - UCT4
Underground Construction - November 2021 - UCT5
Underground Construction - November 2021 - UCT6
Underground Construction - November 2021 - UCT7
Underground Construction - November 2021 - UCT8
Underground Construction - November 2021 - UCT9
Underground Construction - November 2021 - UCT10
Underground Construction - November 2021 - UCT11
Underground Construction - November 2021 - UCT12
https://www.nxtbook.com/gulfenergyinfo/gulfpub/underground-construction-december-2022
https://www.nxtbook.com/gulfenergyinfo/gulfpub/uc_202211
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202210
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202209
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202208
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202207
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202206
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202205
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202204
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202203
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202202
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202201
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202112
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202111
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202110
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202109
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202108
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202107
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202106
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202105
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202104
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202103
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202102
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202101
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202012
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202011
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202010
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202009
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202008
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202007
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202006
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202005
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202004
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202003
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202002
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202001
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201912
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201911
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201910
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201909
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201908
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201907
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201906
https://www.nxtbook.com/nxtbooks/gulfpub/uesi_summer2019
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201905
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201904
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201903
https://www.nxtbook.com/nxtbooks/gulfpub/uesi_winter2019
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201902
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201901
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201812
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201811
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201810
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201809
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201808
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201807
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201806
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201805
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201804
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201803
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201802
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201801
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201712
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201711
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201710
https://www.nxtbook.com/nxtbooks/gulfpub/uc_ditchwitch
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201709
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201708
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201707
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201706
https://www.nxtbookmedia.com