Underground Construction - May 2022 - 34
Manhole Rehab Project
to mobilize its team to get the project underway in August 2021.
The scope of work for IIS was a comprehensive rehab of
the seven-manhole chimney structures. At an average depth of
10 to 11 feet, the project was comprised of 80 vertical feet of
manhole risers, with a five-foot circumference of each structure.
With the proximity of the city of Eagle to the Boise River, and
the corresponding high-groundwater table, four of the seven
risers were experiencing infiltration and inflow; the team used a
hydrophobic pressure grout to address this issue.
The next step was some build back work on all the risers.
Integrity chose a high-early-strength patching material to fill
any voids in the concrete. As part of the surface prep, the contractor
also cut a keyway at the top of the chimneys, below the
grade rings, and a termination key at the spring line - versus
doing a monolithic down to the flow line - using a grinder to
" notch " the concrete.
This would help ensure a good solid termination point at
the edge of the coatings solution, and reduce the possibility
of undercutting, corrosion, disbondment or peeling of the
coating. Once the build back and keyways were completed,
the final step in preparing the surface was pressure washing all
seven of the risers, with a 5,000-psi rotary tip.
When considering a coatings solution for a manhole rehab
project, one option is polyurethane. But in this type of environment,
it would be difficult, time-consuming and expensive
to dry the concrete enough for it to take a typical polyurethane
coating. There was also too-much residual moisture
in the substrate to apply the polyurethane without extensive
surface prep.
As a result, an ultra-high-build epoxy coating was chosen -
Raven 405 from PPG Raven Lining Systems. The 100-percent
solids, zero-volatile, organic-compounds, chemically resistant
epoxy was an ideal solution for the manhole structures. It
could be applied on a saturated surface-dry (SSD) substrate,
saving a significant amount of time.
Raven 405 epoxy was applied direct-to-host, without a
primer, at 150-mil dry-film thickness (DFT). The pressure
washing done beforehand created the required surface profile
for the epoxy to both chemically and mechanically adhere to
the concrete risers.
In some rehab applications, an epoxy coating may seem an
excessive, expensive, and premium solution that isn't needed.
But with an environment with such high exposure to extreme
levels of H₂S, the epoxy was critical to providing a long, useful
life for the manhole risers - " as good as new, " for most any
sanitary sewer infrastructure application.
48 hours
Integrity Inspection Solutions works on the manhole coatings project in
Eagle, Idaho.
Once the film was dry (approximately four to five hours),
a final step was a comprehensive holiday test in the seven
chimneys, following ASTM and NACE industry standards.
The tests, using specialized, high-voltage equipment, ensured
there were no inconsistencies or imperfections in the 150-mil
DFT surface of the epoxy coating, such as discontinuities, pinholes,
holidays and voids.
Holiday tests are particularly important when applying
anti-corrosive coatings, as undetected holidays leave the underlying
substrate (concrete, masonry, metal) susceptible to
corrosion at those locations.
From start to finish, the IIS team took 48 hours to get the
job done. It was a quick and efficient project, made possible
by the knowledge and expertise of the team, but also by the
time-saving features of the 405 epoxy. With the ability to apply
the coating on an SSD substrate, and the brief window
from time of application to holiday tests, it proved an effective
solution as part of a long-term, ongoing maintenance plan for
any sanitary sewer district. *
ABOUT THE AUTHOR: Randy Gonzalez is the West Region Technical
Manager for PPG PMC Raven Lining Systems. He can be reached at
760-685-7784, or at gonzalezr@ravenlining.com.
FOR MORE INFORMATION:
Manhole after being coated.
34 MAY 2022 | UCONonline.com
Integrity Inspection Solutions, (208) 442-4470, iispipeline.com
Raven Lining Systems, (800) 321-0906, ravenlining.com
http://www.iispipeline.com
http://www.ravenlining.com
http://www.UCONonline.com
Underground Construction - May 2022
Table of Contents for the Digital Edition of Underground Construction - May 2022
Contents
Underground Construction - May 2022 - Cover1
Underground Construction - May 2022 - Cover2
Underground Construction - May 2022 - Contents
Underground Construction - May 2022 - 4
Underground Construction - May 2022 - 5
Underground Construction - May 2022 - 6
Underground Construction - May 2022 - 7
Underground Construction - May 2022 - 8
Underground Construction - May 2022 - 9
Underground Construction - May 2022 - 10
Underground Construction - May 2022 - 11
Underground Construction - May 2022 - 12
Underground Construction - May 2022 - 13
Underground Construction - May 2022 - 14
Underground Construction - May 2022 - 15
Underground Construction - May 2022 - 16
Underground Construction - May 2022 - 17
Underground Construction - May 2022 - 18
Underground Construction - May 2022 - 19
Underground Construction - May 2022 - 20
Underground Construction - May 2022 - 21
Underground Construction - May 2022 - 22
Underground Construction - May 2022 - 23
Underground Construction - May 2022 - 24
Underground Construction - May 2022 - 25
Underground Construction - May 2022 - 26
Underground Construction - May 2022 - 27
Underground Construction - May 2022 - 28
Underground Construction - May 2022 - 29
Underground Construction - May 2022 - 30
Underground Construction - May 2022 - 31
Underground Construction - May 2022 - 32
Underground Construction - May 2022 - 33
Underground Construction - May 2022 - 34
Underground Construction - May 2022 - 35
Underground Construction - May 2022 - 36
Underground Construction - May 2022 - 37
Underground Construction - May 2022 - 38
Underground Construction - May 2022 - 39
Underground Construction - May 2022 - 40
Underground Construction - May 2022 - 41
Underground Construction - May 2022 - 42
Underground Construction - May 2022 - Cover3
Underground Construction - May 2022 - Cover4
https://www.nxtbook.com/gulfenergyinfo/gulfpub/underground-construction-december-2022
https://www.nxtbook.com/gulfenergyinfo/gulfpub/uc_202211
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202210
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202209
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202208
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202207
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202206
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202205
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202204
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202203
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202202
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202201
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202112
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202111
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202110
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202109
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202108
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202107
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202106
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202105
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202104
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202103
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202102
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202101
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202012
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202011
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202010
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202009
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202008
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202007
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202006
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202005
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202004
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202003
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202002
https://www.nxtbook.com/nxtbooks/gulfpub/uc_202001
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201912
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201911
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201910
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201909
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201908
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201907
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201906
https://www.nxtbook.com/nxtbooks/gulfpub/uesi_summer2019
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201905
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201904
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201903
https://www.nxtbook.com/nxtbooks/gulfpub/uesi_winter2019
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201902
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201901
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201812
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201811
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201810
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201809
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201808
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201807
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201806
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201805
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201804
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201803
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201802
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201801
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201712
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201711
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201710
https://www.nxtbook.com/nxtbooks/gulfpub/uc_ditchwitch
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201709
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201708
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201707
https://www.nxtbook.com/nxtbooks/gulfpub/uc_201706
https://www.nxtbookmedia.com