Figure 8. A grid-forming inverter BESS installed in an industrial estate in northern Melbourne to support a local end-of-line feeder; all system
components are transportable. (Source: Hitachi Energy; used with permission.)
which compares responses to a rate-of-change-of-frequency
(RoCoF) event from a VSM with optimal damping
and synchronous machines in a simulation. Moreover,
each parameter influences a different part of the stiffness
spectrum, so the entire dynamic stiffness can be
shaped. Finally, should the characteristics of the grid
change, the parameter values can be adaptively varied
during operation.
Grid-Forming Inverters With
VSM Functionality in Operation
Grid Energy Storage System, Victoria, Australia
A 1-MW/1-MWh grid-forming BESS was installed in an
industrial estate in Melbourne, Victoria, Australia, to
Microgrid
Batteries
Plus System (Control)
PowerStore (Inverters)
Substation
demonstrate end-of-line distribution feeder grid support,
with features including peak demand management,
improved power system quality, network investment
deferral, and seamless emergency islanding. Figure
8 shows the installation, with Figure 9 giving a
system overview.
Two aims of the project were paramount. First, given
Ring
Diesel
Generator
Figure 9. A grid energy storage system for end-of-line distribution
feeder grid support.
46
IEEE Electrification Magazine / MARCH 2022
Seamless Islanding
When transitioning from grid-connected to island mode,
as seen in Figure 10, the local generation increases its
power output so that the power flow across the upstream
breaker is zero and the microgrid is entirely supplying
Main Unit
the prevalence of bushfires in Victoria, the " bumpless "
islanding and reconnection may be used to mitigate the
effect of fires on the supply to remote and rural locations.
In such cases, a feeder would be de-energized just prior to
a bushfire passing through an area, with disconnected
communities supplied by the grid-forming BESS. Once the
fire moved away and the feeder was checked for damage,
the line would be re-energized before the microgrid performed
a " bumpless " transition back onto the grid. The second
important use of the energy storage is to manage peak
demand on stressed feeders, therefore deferring investment
in network augmentation. By embedding a generation
source close to the load, the utility plans to study the
effects this will have on postponing network investment
involved with upgrading feeder lines to support increased
loads. The side effect of having a grid-forming inverter connected
to the grid is that it improves local power quality,
such as the power factor, harmonics, flicker, and negative
sequence voltage.

IEEE Electrification - March 2022

Table of Contents for the Digital Edition of IEEE Electrification - March 2022

Contents
IEEE Electrification - March 2022 - Cover1
IEEE Electrification - March 2022 - Cover2
IEEE Electrification - March 2022 - Contents
IEEE Electrification - March 2022 - 2
IEEE Electrification - March 2022 - 3
IEEE Electrification - March 2022 - 4
IEEE Electrification - March 2022 - 5
IEEE Electrification - March 2022 - 6
IEEE Electrification - March 2022 - 7
IEEE Electrification - March 2022 - 8
IEEE Electrification - March 2022 - 9
IEEE Electrification - March 2022 - 10
IEEE Electrification - March 2022 - 11
IEEE Electrification - March 2022 - 12
IEEE Electrification - March 2022 - 13
IEEE Electrification - March 2022 - 14
IEEE Electrification - March 2022 - 15
IEEE Electrification - March 2022 - 16
IEEE Electrification - March 2022 - 17
IEEE Electrification - March 2022 - 18
IEEE Electrification - March 2022 - 19
IEEE Electrification - March 2022 - 20
IEEE Electrification - March 2022 - 21
IEEE Electrification - March 2022 - 22
IEEE Electrification - March 2022 - 23
IEEE Electrification - March 2022 - 24
IEEE Electrification - March 2022 - 25
IEEE Electrification - March 2022 - 26
IEEE Electrification - March 2022 - 27
IEEE Electrification - March 2022 - 28
IEEE Electrification - March 2022 - 29
IEEE Electrification - March 2022 - 30
IEEE Electrification - March 2022 - 31
IEEE Electrification - March 2022 - 32
IEEE Electrification - March 2022 - 33
IEEE Electrification - March 2022 - 34
IEEE Electrification - March 2022 - 35
IEEE Electrification - March 2022 - 36
IEEE Electrification - March 2022 - 37
IEEE Electrification - March 2022 - 38
IEEE Electrification - March 2022 - 39
IEEE Electrification - March 2022 - 40
IEEE Electrification - March 2022 - 41
IEEE Electrification - March 2022 - 42
IEEE Electrification - March 2022 - 43
IEEE Electrification - March 2022 - 44
IEEE Electrification - March 2022 - 45
IEEE Electrification - March 2022 - 46
IEEE Electrification - March 2022 - 47
IEEE Electrification - March 2022 - 48
IEEE Electrification - March 2022 - 49
IEEE Electrification - March 2022 - 50
IEEE Electrification - March 2022 - 51
IEEE Electrification - March 2022 - 52
IEEE Electrification - March 2022 - 53
IEEE Electrification - March 2022 - 54
IEEE Electrification - March 2022 - 55
IEEE Electrification - March 2022 - 56
IEEE Electrification - March 2022 - 57
IEEE Electrification - March 2022 - 58
IEEE Electrification - March 2022 - 59
IEEE Electrification - March 2022 - 60
IEEE Electrification - March 2022 - 61
IEEE Electrification - March 2022 - 62
IEEE Electrification - March 2022 - 63
IEEE Electrification - March 2022 - 64
IEEE Electrification - March 2022 - 65
IEEE Electrification - March 2022 - 66
IEEE Electrification - March 2022 - 67
IEEE Electrification - March 2022 - 68
IEEE Electrification - March 2022 - 69
IEEE Electrification - March 2022 - 70
IEEE Electrification - March 2022 - 71
IEEE Electrification - March 2022 - 72
IEEE Electrification - March 2022 - 73
IEEE Electrification - March 2022 - 74
IEEE Electrification - March 2022 - 75
IEEE Electrification - March 2022 - 76
IEEE Electrification - March 2022 - 77
IEEE Electrification - March 2022 - 78
IEEE Electrification - March 2022 - 79
IEEE Electrification - March 2022 - 80
IEEE Electrification - March 2022 - Cover3
IEEE Electrification - March 2022 - Cover4
https://www.nxtbook.com/nxtbooks/pes/electrification_december2022
https://www.nxtbook.com/nxtbooks/pes/electrification_september2022
https://www.nxtbook.com/nxtbooks/pes/electrification_june2022
https://www.nxtbook.com/nxtbooks/pes/electrification_march2022
https://www.nxtbook.com/nxtbooks/pes/electrification_december2021
https://www.nxtbook.com/nxtbooks/pes/electrification_september2021
https://www.nxtbook.com/nxtbooks/pes/electrification_june2021
https://www.nxtbook.com/nxtbooks/pes/electrification_march2021
https://www.nxtbook.com/nxtbooks/pes/electrification_december2020
https://www.nxtbook.com/nxtbooks/pes/electrification_september2020
https://www.nxtbook.com/nxtbooks/pes/electrification_june2020
https://www.nxtbook.com/nxtbooks/pes/electrification_march2020
https://www.nxtbook.com/nxtbooks/pes/electrification_december2019
https://www.nxtbook.com/nxtbooks/pes/electrification_september2019
https://www.nxtbook.com/nxtbooks/pes/electrification_june2019
https://www.nxtbook.com/nxtbooks/pes/electrification_march2019
https://www.nxtbook.com/nxtbooks/pes/electrification_december2018
https://www.nxtbook.com/nxtbooks/pes/electrification_september2018
https://www.nxtbook.com/nxtbooks/pes/electrification_june2018
https://www.nxtbook.com/nxtbooks/pes/electrification_december2017
https://www.nxtbook.com/nxtbooks/pes/electrification_september2017
https://www.nxtbook.com/nxtbooks/pes/electrification_march2018
https://www.nxtbook.com/nxtbooks/pes/electrification_june2017
https://www.nxtbook.com/nxtbooks/pes/electrification_march2017
https://www.nxtbook.com/nxtbooks/pes/electrification_june2016
https://www.nxtbook.com/nxtbooks/pes/electrification_december2016
https://www.nxtbook.com/nxtbooks/pes/electrification_september2016
https://www.nxtbook.com/nxtbooks/pes/electrification_december2015
https://www.nxtbook.com/nxtbooks/pes/electrification_march2016
https://www.nxtbook.com/nxtbooks/pes/electrification_march2015
https://www.nxtbook.com/nxtbooks/pes/electrification_june2015
https://www.nxtbook.com/nxtbooks/pes/electrification_september2015
https://www.nxtbook.com/nxtbooks/pes/electrification_march2014
https://www.nxtbook.com/nxtbooks/pes/electrification_june2014
https://www.nxtbook.com/nxtbooks/pes/electrification_september2014
https://www.nxtbook.com/nxtbooks/pes/electrification_december2014
https://www.nxtbook.com/nxtbooks/pes/electrification_december2013
https://www.nxtbook.com/nxtbooks/pes/electrification_september2013
https://www.nxtbookmedia.com