Remote - Winter 2013 - (Page 10)
Feature Article
Approaches to Powering Telecom Sites
Arthur D. Sams, President
Polar Power, Inc.
Reducing energy costs presents the largest opportunity in telecom for reducing operational costs. The same principles discussed here can be applied
to remote monitoring, and SCADA / RTU sites. Running an AC generator
24/7 is the traditional but least efficient method of powering an off grid site.
Maintenance and fuel costs are too high and the reliability is poor.
3 kW to 15 kW
DC generators are
now replacing 20
kVA to 40 kVA
AC generators
in off grid and
backup applications. Larger AC
generators are
used because they
have proven to last longer than smaller AC generators. Additional factors
requiring over sizing the AC generator in relation to the load include:
*
AC generators less than 10 kVA are aimed at temporary construction and standby use. These applications require low cost and do not
need long life. The 5 to 10 kVA AC generators typically last a year
before requiring replacement in off grid and solar PV applications.
*
You cannot reliably operate an AC generator close to its rated capacity and maintain frequency, voltage regulation, and prevent the
circuit breaker from tripping.
*
Air-conditioning starting current requirements
*
Providing the power capacity to recharge the batteries and power
the load after a disruption in power
Cycling for Both Off-Grid and On-Grid Applications with
Poor Utility Service
Field trials have shown fuel savings of more than 40 percent when
using a cycling generator as opposed
to a generator operating 24/7. Reliability is enhanced and maintenance
is reduced using the cycling solution.
A - AC Cycling: AC generators
can be used with rectifiers / battery
chargers and operated in a cycle
charging fashion; this offers a fuel
saving advantage over operating an
AC generator 24/7. The disadvantages
of the AC generator cycling are:
*
There is a power loss of 8
to 15 percent through the
battery charger/rectifier; the
generator is required to produce more power, consuming more fuel.
*
The AC generator is less efficient than the DC PM generator in converting the engine's power into electricity. The DC generator is about
20 percent more fuel efficient than the AC generator.
*
The AC generator has to be oversized because its power output cannot be regulated. An over current condition trips a circuit breaker,
requiring a manual reset. Larger generators with larger engine
displacements consume more fuel.
*
The AC generator is fixed speed; fuel consumption diminishes only
slightly with decreasing loads as shown in the graph.
*
CAPEX costs are higher with the AC generator cycling in off grid
systems. The system requires an AC generator, transfer switch, battery charger/rectifier and a system controller.
*
OPEX costs are higher with the AC cycling as the system consumes
more fuel and requires maintenance.
10
www.RemoteMagazine.com
B - DC Cycling: DC Cycling is 25 to 40 percent more fuel efficient than
AC cycling. As
shown in the graph
below, the concept
behind DC cycling
is to allow the generator to operate at
its peak efficiency
and shut off during
low load demand,
letting the batteries
power the load.
This saves fuel and
engine maintenance. Also shown
in the graph is the
DC generator's
additional fuel
reduction due to the variable speed feature of the DC generator. As the load
decreases, so does the engine speed, allowing the engine to continuously
operate at near its peak efficiency.
The power output of a Polar DC generator is regulated so can operate
closer to the ideal engine power curve (there are no circuit breakers to trip).
This saves fuel because it makes use of smaller displacement engines. In the
chart we show the DC generator operating at 80 percent of its rated power.
Sizing
Sizing an AC generator requires that its capacity be greater than the sum
of all the loads that may operate at the same time. This would include the
surges for air-conditioning startup. Typically the sizing of the DC generator
into an application is based on the amount of energy required in a 24 hour
period plus charging losses in the battery divided by the desired generator
runtime within the same period.
AC vs. DC Generator
Field trials have shown the DC generator having a 70 percent and greater
fuel reduction over the conventional AC generators operating 24/7.
You can efficiently operate
the DC generator
at 100 percent of
its power rating.
In comparison, the
AC generator is
operating a larger
engine at less than
50 percent of its rating. In the graph above, the red line representing the AC
generator is consuming more fuel than the blue line for the DC generator.
The AC generator running while the load is at a minimum power level
represents a significant waste of fuel. Using the DC cycling approach, the
DC generator is off and the load is powered by the battery.
DC Hybrid Power Solution - Combining Renewable
Energy and Fuel
The Hybrid solution consists of a DC generator which charges the battery and powers the load at the same time. The DC generator is designed
to shut down after the battery is charged and the load demand is low. The
battery provides power to the load while the generator is shut down. This
is an energy efficient alternative to an AC generator operating 24/7. The
hybrid power solution allows the convenient integration of solar and wind
for further fuel reduction and lower generator maintenance. Solar and wind
can be added at any time and incrementally.
For most telecom applications the use of 100 percent solar and wind
http://www.RemoteMagazine.com
Table of Contents for the Digital Edition of Remote - Winter 2013
Editor’s Choice
Message Oriented Middleware - The Future of SCADA
Enhanced SCADA Access and Big Data Lead to New Analytics & Optimization Capabilities
Approaches to Powering Telecom Sites
Satellite Communications for Water Metering and Other Water Applications
Remote Magazine Launches Internet of Things North America
Geospatially Integrated Surveillance Systems
Tier 1 Operator Case Study: Intelligent Site Management
SCADA - The Brain of the Smart Grid
SCADA
Networking
Security
Onsite Power
Industry News
Remote - Winter 2013
https://www.nxtbook.com/nxtbooks/webcom/remote_2016winter
https://www.nxtbook.com/nxtbooks/webcom/remote_2016fall
https://www.nxtbook.com/nxtbooks/webcom/remote_2016
https://www.nxtbook.com/nxtbooks/webcom/remote_2016spring
https://www.nxtbook.com/nxtbooks/webcom/remote_2015fall
https://www.nxtbook.com/nxtbooks/webcom/remote_2015m2m
https://www.nxtbook.com/nxtbooks/webcom/remote_2015spring
https://www.nxtbook.com/nxtbooks/webcom/remote_industrialnetworking2014
https://www.nxtbook.com/nxtbooks/webcom/remote_2014fall
https://www.nxtbook.com/nxtbooks/webcom/remote_2014m2m
https://www.nxtbook.com/nxtbooks/webcom/remote_2014spring
https://www.nxtbook.com/nxtbooks/webcom/remote_2013winter
https://www.nxtbook.com/nxtbooks/webcom/remote_2013m2m
https://www.nxtbook.com/nxtbooks/webcom/remote_2013fall
https://www.nxtbook.com/nxtbooks/webcom/remote_2013summer
https://www.nxtbook.com/nxtbooks/webcom/remote_2013spring
https://www.nxtbook.com/nxtbooks/webcom/remote_2012winter
https://www.nxtbook.com/nxtbooks/webcom/remote_2012m2m
https://www.nxtbook.com/nxtbooks/webcom/remote_2012fall
https://www.nxtbook.com/nxtbooks/webcom/remote_2012summer
https://www.nxtbook.com/nxtbooks/webcom/remote_2012scada
https://www.nxtbook.com/nxtbooks/webcom/remote_2012spring
https://www.nxtbook.com/nxtbooks/webcom/remote_201112
https://www.nxtbook.com/nxtbooks/webcom/remote_201110
https://www.nxtbook.com/nxtbooks/webcom/remote_201108
https://www.nxtbookmedia.com